Invoice anatomy and mistakes · 6 min read
Milestone payments: how to split a freelance project into paid stages, common splits like 30/40/30, and a payment schedule to copy
Milestone payments split a project fee into stages, each paid when a deliverable is approved. Common splits like 30/40/30, and a sample payment schedule.
- Written by
- Arun Chauhan
- Published
Milestone payments split a project's fee into stages, and the client pays each stage when you reach a defined point, such as approved designs or a finished first draft. A common split is 30% at the start, 40% at a midpoint and 30% on delivery, though 50/50 and 30/30/40 are also widely used. Each milestone has a clear deliverable, an amount and its own invoice. You are never more than one stage of work away from your last payment.
On a two-week job, a single invoice at the end is usually fine. On a three-month project, waiting until the end means you fund the whole thing yourself, and you carry all the risk if the client goes quiet. Milestones fix both.
Choosing the milestones
A good milestone is something both of you can point to and agree is done. "50% complete" is not a milestone, because nobody can check it. "Homepage design approved" is.
Useful milestones tend to be:
- A deliverable the client sees. Designs, a draft, a working staging site, a rough cut.
- A point where the client signs off. Approval of one stage before the next starts.
- Roughly even in effort. So each payment matches a similar chunk of your time.
Three to five milestones suits most freelance projects. Fewer, and the gaps get long. More, and you spend your time invoicing.
Common splits
| Split | Typical use | Notes |
|---|---|---|
| 50 / 50 | Short projects, 2 to 6 weeks | Half to start, half on delivery |
| 30 / 40 / 30 | Medium projects with a clear middle stage | The middle stage often holds the most work |
| 30 / 30 / 40 | Projects where the client wants more held back to the end | Gives the client more comfort, gives you less |
| 25 / 25 / 25 / 25 | Longer projects, 3 months and up | Even stages, even cash flow |
| 40 / 30 / 30 | New clients, or where early work is heaviest | Front-loads your protection |
No split is standard everywhere. Match it to where the work actually happens. If the design phase is half the effort, it should be close to half the fee.
The first payment usually works as a deposit: work starts when it lands. The deposit invoice post covers how to word that first invoice.
A worked schedule with real dates
A designer in Lisbon agrees a brand identity and website project with a client for EUR 9,000. The project runs from March to May 2027. They agree a 30/40/30 split and 7-day payment terms on each invoice.
| Milestone | Deliverable that triggers it | Share | Amount | Invoiced | Due |
|---|---|---|---|---|---|
| 1. Kick-off | Signed agreement | 30% | EUR 2,700 | 1 March 2027 | 8 March 2027 |
| 2. Design approved | Logo, brand guide and page designs signed off | 40% | EUR 3,600 | 9 April 2027 | 16 April 2027 |
| 3. Launch | Website live, files handed over | 30% | EUR 2,700 | 21 May 2027 | 28 May 2027 |
| Total | 100% | EUR 9,000 |
Notice the invoice dates follow the deliverables, not the calendar. If the client takes an extra two weeks to approve the designs, milestone 2 moves with them. Write that into the agreement, so nobody expects a payment on a fixed date that no longer makes sense.
Short payment terms suit milestone invoices. On 30-day terms, the client would pay milestone 2 in mid-May, by which point you are well into the final stage on their credit. Seven or 14 days keeps payments close to the work.
Put it in the agreement first
Agree the schedule before work starts, in your quote or contract. For each milestone, write down:
- What has to be delivered.
- What counts as approval: a reply, a signature, or a set number of days without comments.
- The amount and the percentage.
- The payment terms on each invoice.
Then add two clauses that save a lot of trouble:
If feedback on a milestone isn't received within 10 working days of delivery, the milestone is treated as approved and invoiced.
Work on the next milestone starts once the previous milestone's invoice is paid.
The first stops a project stalling forever on "we'll get back to you". The second makes sure you don't do stage three while stage two is unpaid. If you'd rather not be that strict, at least agree how far into the next stage you will go before pausing.
Writing each milestone invoice
Each invoice is a normal invoice with its own number. Make it easy to place in the project:
| Item | Amount |
|---|---|
| Brand identity and website, milestone 2 of 3: design approved (40% of EUR 9,000) | EUR 3,600 |
That one line tells the client's finance team which project it is, which stage, what share of the total, and what the total is. Some freelancers also list the milestones already paid in a note, so the client sees progress at a glance:
Milestone 1 (EUR 2,700) paid 6 March 2027. This invoice: milestone 2. Remaining after this: milestone 3, EUR 2,700, invoiced at launch.
When the scope changes mid-project
Extra work doesn't belong inside an existing milestone. Price it as a change, get it agreed in writing, then either add it to the next milestone's invoice as its own line or bill it separately. Changing a milestone's percentage after the fact makes the schedule hard to follow.
If the client cancels part way through, the milestones make the conversation simpler. Paid milestones stay paid. The current stage is usually billed for the work done so far, as your agreement sets out.
Milestone invoices in BillMinute
BillMinute has no milestone feature, but each milestone is just its own invoice, which BillMinute handles well. Create one invoice per stage when you reach it, with a line such as "Milestone 2 of 3: design approved (40% of EUR 9,000)", and send it with your payment details. You'll see when the client opens it, and an automatic reminder goes out if it is missed. The free plan covers up to 10 invoices a month; Pro adds reminders before the due date. See pricing.